Installation
A typical Grit King® Process
can be installed in 3 to 5 days, depending on the scope of
the contract.
Typically the mechanical installation includes for the
off-loading of the individual component items which usually
comprise the following items: Separator, Pump, Classifier,
and interconnecting pipework. These items are positioned
and bolted down on prepared foundations constructed by others
to HRD Technologies' dimensions. The items are then connected
together with the pipework.
If electrical installation is required then cable ducts
will be provided by the Client and HRD Technologies will
cable between the items and the Control Panel. |
 |