Installation Instructions

Typical installation procedures include:

  1. Excavation of the detention/infiltration volume
  2. Laying a geotextile (for infiltration) or a membrane (for detention)
  3. Installing the Stormbloc™ blocks, Stormbloc™ Inspect Chambers, end plates, and connecting inlet/outlet pipework
  4. Wrapping the geotextile or sealing the membrane around the finished Stormbloc™ volume
  5. Backfilling the sides and top of the system

Please call or inquire online for a detailed installation manual or Click here to download user manual.